The Eiraman Method · specification 0.3
Specification 0.3 · 25 November 2026 · Supersedes specification 0.2. Changes are listed in the log at the end.
Courtesy translation. This is a courtesy translation of the Italian text. In case of any difference, the Italian original prevails.
Status. Version 0.3 of 25 November 2026.
Conventions.
- Sentences with must or may not are normative rules: an application conforms to Eiraman only if it respects them.
- Sentences marked Guidance give recommended values or practices that the project mandate may change.
- Implementation choices belong to the tool, not to this specification.
1. What Eiraman is
Eiraman is a Vibe Coding method for organisations. The human does not read the code: they govern as a manager, through a mandate, principles and delegation. A system of AI agents executes the work, checks itself through competitive mechanisms and handles operational exceptions. Every release can be reconstructed from evidence and costs.
Why it exists. Human-in-the-loop approaches, where a person approves or corrects each AI step, and human-on-the-loop approaches, where a person monitors execution and steps in on exceptions, as well as human code review, help little where there are no development teams. The definitions follow the EU Ethics Guidelines for Trustworthy AI (2019). They have two limits:
- the proliferation of point checks leads to approvals like accepting a software licence: nobody reads them;
- they confine AI to application development instead of putting it at the service of business users.
Eiraman overcomes them through planning and a multi-LLM mode: within the same project several models work independently as AI Coordinator, executors and reviewers.
Founding principle. Eiraman starts again from traditional management methods and applies them to AI. Agents are governed the way a manager governs an organisation: objectives and mandate, delegation, roles and teams, planning, risk management, reviews and retrospectives. This is why the human is a Human as a Manager. Every rule of the method transposes a known management practice, adapted to what changes when the one executing is an agent rather than a person.
| Management practice | Transposition in Eiraman | What changes with agents | Where |
|---|---|---|---|
| Mandate, objectives, Management by Objectives | Human Manager mandate, Vision, success criteria and stop criteria | Objectives become executable, measured criteria | §2, §5 |
| Delegation and responsibility matrix (RACI) | 3D escalation Deny/Delegate/Do, RACI | Delegation is decided on reversibility and silence is never consent | §2, §3 |
| Organisation chart, staff planning, seniority | Pyramid of AI Squads, Role Profiles, Unit Cost | Roles are instantiated on different models and recomposed at every retrospective | §4 bis, §9 |
| Scrum and Scrum of Scrums | Teams per Work Package, AI Scrum Master, AI Coordinator | No human timeboxes: the limits are cost, context and quotas | §4 bis, §5 |
| Design Thinking | Discovery with divergence and convergence across models | Guardrails are needed because agents lack a person's contextual judgement | §5 |
| Enterprise architecture (TOGAF) and Composable Architecture | Architectural views, Backbone/Brain/interfaces/Hairs | Priority prevents the patchworks that AI would easily produce | §6 bis |
| Scope and risk management | Versioned Principles and Decisions, Risk Log, applicability levels | Risk is limited up front because specialist competence lives in the profiles, not in the single project | §5, §8, §10 |
| Quality and independent control | Closure on evidence, independent verifiers, competitive mechanisms | Agents do not tire: competition between candidates is sustainable, if the cost justifies it | §4, §6 |
| Management reporting | Cycle review, bad news first, blocking completeness check | An agent's summary may be flattering and is checked against the records | §5, §8 |
The method has three components:
- Framework. Roles, delegation, work cycle, architectural conventions, proofs of completion and applicability levels. Each project records the version of the method it adopts.
- Development Environment. The environment in which the method runs. It hosts the AI Coordinator, executions, logs and verification tools, and it enforces Deny (§3, §7). The AI Coordinator configures and runs it on behalf of the business owner. Calls to external services depend on the project's delegation. State, logs, repository and secrets stay local; only the prompts and data sent to the engines and connectors authorised by the mandate leave the environment.
- Projects. Applications whose development tests the method and helps refine it. An application may incorporate part of the method (§11).
The tool that puts the method into practice is one implementation of it. It must respect the normative rules and may not add rules of its own and present them as Eiraman. An application conforms only if it respects all normative rules; otherwise it publishes a declaration of partial conformity (§11).
Context principles
- Specialist competence lives in Role Profiles, not in every project. Eiraman does not replace those who develop software: it moves their competence into Role Profiles and their qualification at framework level (§9), from where it guides agents across many projects. Production thus moves closer to those who have the need. The human operator of the project is a business user: they decide on functional and economic matters and do not stand in for the AI roles on technology, applications or security.
- Human as a Manager. The human acts up front, with management tools: mandate, objectives, principles, delegation, reserved matters, budget, success criteria. They work mainly at the strategic level and, for business decisions only, at the tactical level. They do not supervise execution. Exceptions and operational autonomy belong to the AI system.
- Exclusions. The method does not apply to AI systems that are prohibited or high-risk under the AI Act, nor to the other out-of-scope cases in §10.
Operating model
Eiraman brings the main reference frameworks into an agentic form, adapting them to the differences between people and machines:
| Framework | How Eiraman uses it | Where |
|---|---|---|
| Design Thinking and brainstorming | Divergence across several models, convergence by an analyst, the Human Manager steps in at fixed gates | §5 |
| Composable Architecture | Components by function, developed in independent Work Packages and built in order of priority | §6 bis |
| TOGAF ADM | Business, functional (applications), data and infrastructure (technology) views in the architecture document | §5, §6 bis |
| Scrum and Scrum of Scrums | AI Squads per Work Package with an AI Scrum Master, coordinated by the AI Coordinator | §4 bis |
| DevSecOps | Readable Git, automated tests, security by design | §6 |
Two differences between people and machines drive the adaptations:
- Machines do not have the limits of human interaction. They analyse content and learn frameworks much faster. Scrum's limits, such as team size or Sprint length, no longer depend on human capacity but on the systems: cost, context window, provider quotas.
- Agents lack a person's contextual judgement: they follow instructions literally and do not realise on their own when they are drifting out of scope. Open activities such as brainstorming need tighter boundaries and guardrails than with a human team: defined roles and behaviours, number of rounds, convergence criteria, permitted data.
Two results, accepted separately
Acceptance of the software and acceptance of the deliverable the software produces remain separate. Example: in NUR a software increment may introduce an editorial check. To close the package, the check must be shown to work. The document NUR produces goes through its own editorial review. A rejected PDF can be the successful proof of the check that prevented its delivery.
2. Responsibilities
Human Manager. The business person who governs the project. In the original version this person holds two roles: Product Owner and Business Architect.
- Describes users and process.
- Approves Vision, Principles, success criteria, mandate, spending, project class and level upgrades.
- Decides the Do escalations, approves the next governance cycle and accepts or rejects the result.
- May authorise linking an account or folder through the platform's native consent.
- Receives technical decisions only once translated into functions, costs, time and impact on users and data.
AI Coordinator. Its Role Profile is described in §9.
- Acquires the authorised repository, configures engines and tools within permissions, assigns credentials within the permissions granted, checks availability and budget.
- Prepares Waves, assigns Work Packages, validates results and conformity, updates the plan and runs retrospectives.
- Manages start-up, diagnosis, suspension, resumption, release within mandate and restore.
Specialist AI roles. Analyst, architects, AI Scrum Master, executors, testers and AI reviewers work with qualified Role Profiles and respect their limits. They take the technical decisions. The tester has access to requirements, contracts, data and expected results. Their first assessment is made independently of the executor's discussion.
Process reviewer. An independent agent, running on a different model from the AI Coordinator's. It samples closed Waves and checks that due escalations reached the Human Manager (§3, E6) and that closures are backed by evidence (§6).
Maintainers. Expert members of the organisation that publishes the method, outside the projects. They qualify Role Profiles, document templates and the gate checklist (§9).
Who answers for what
Internal accountability. Everyone answers for what they decide.
- The Human Manager answers for decisions within their remit and for using the method within the qualified scope.
- The AI Coordinator and the AI roles answer in an operational sense: every closure has evidence and every error becomes a retrospective case. This is not legal liability.
- Maintainers answer for the profiles' conformity to their sources at the time of qualification, not for individual projects.
Liability towards third parties. It lies with the owner: the individual at level 0, the organisation at levels 1 and 2.
- At levels 1 and 2 the Human Manager acts under a formal mandate from the organisation. Without that mandate the project stays at level 0.
- The owner exercises this responsibility through mandate, class and acceptance, and demonstrates due diligence with Eiraman evidence (§8, third-party evidence pack).
| Activity | Human Manager | Owner | AI Coordinator | AI roles, incl. testers and reviewers | Process reviewer | Maintainers |
|---|---|---|---|---|---|---|
| Mandate, Principles, class and level | A/R | I; at levels 1–2 grants the mandate | C | R for the class (compliance gate) | — | — |
| Technical decisions | I, in translated form | — | Operational A | R | V | — |
| Technical closure of the package | — | — | Operational A / R | R | V | — |
| Business acceptance | A/R | I | C | — | — | — |
| Release to users | A towards the organisation | A towards third parties | R | C | V | — |
| Profile qualification | — | — | I | — | — | A/R |
| Incidents and data breaches | I; decides the Do | A; notification under Art. 33 GDPR | R | R | V | — |
R = executes · A = accountable · C = consulted · I = informed · V = verifies afterwards, by sampling.
3. 3D escalation
Deny. The environment, not the agent, blocks an action forbidden by the mandate or outside the level, and records why. The AI Coordinator looks for an authorised alternative. If there is none, it suspends the affected work.
Delegate. AI roles decide two-way doors (decisions that can be undone) on their own: reversible decisions with a known cost, within budget — engine, attempt, fix, restore. Every choice stays linked to its package.
The distinction between Type 1 decisions (irreversible, "one-way doors (decisions that cannot be undone)") and Type 2 decisions (reversible, "two-way doors") comes from Jeff Bezos's 2015 letter to Amazon shareholders. Bezos warns above all against handling Type 2 decisions with a heavyweight process: in Eiraman this is over-escalation. The opposite risk is under-escalation. Both are measured (E6).
Do. These always go to the Human Manager:
- one-way doors;
- the mandate's reserved matters: impact on Vision, Principles or success criteria, personal data, third parties, new suppliers, spending above threshold;
- changes to a Decision;
- new access;
- changes of project class and level upgrades. Level downgrades are automatic (§10).
When reversibility is in doubt, the decision is a one-way door. The Do presents, in functional and economic terms:
- impact;
- options;
- recommendation;
- evidence;
- deadline;
- what happens if there is no answer.
A change to a Decision includes a SWOT. After the choice, execution returns to the AI Coordinator.
Rules against under-escalation
| # | Rule |
|---|---|
| E1 | The mandate lists reserved matters alongside delegation. What goes to the Human Manager is the business impact of the reserved matter, translated into functions, costs, time and impact on users and data. The technical choice stays with the AI roles. Reserved matters prevail over K7. |
| E2 | Reversibility is the criterion between Delegate and Do. |
| E3 | Every non-trivial choice is recorded as a micro-decision, with the alternative, estimated reversibility, cost of rollback and reserved matters considered. |
| E4 | Whether a decision must go to the Human Manager is decided by a classifier running on a model different from the AI Coordinator's. If the two disagree, the decision goes up. |
| E5 | Deviations from plan, including class changes, add up in a drift budget cumulated over the project and reported per governance cycle. Beyond the mandate's threshold, a mandate review is triggered. |
| E6 | The process reviewer measures under-escalation (reserved decisions not brought to the Human Manager, over all reserved decisions) and over-escalation (Do escalations that fell within delegation, over all Do escalations). In the NUR pilot, and then in the first project of every new adoption, the Human Manager reviews once a sample of about 20 autonomous decisions to calibrate the reviewer. |
Deadlines and urgencies
Silence never approves a Do.
- Until there is an answer, the affected package stays suspended and independent work continues.
- At the deadline the Human Manager receives a reminder.
- At the second deadline the package leaves the Wave and the cycle review reports it as a missing decision.
- The irreversible option is never executed without an answer.
- Urgent containment. The mandate lists pre-authorised, reversible containment actions: restore, credential revocation, disabling a function, temporary suspension of the service. The AI Coordinator executes them immediately and opens an urgent Do. Any action not on the list follows the ordinary Do rule.
- Guidance. Ordinary Do: 3 working days plus another 3. Urgent Do: 4 hours.
4. Competitive mechanisms
Rationale. The principles of the theory of human cooperation are applied to AI models and shifted towards more competitive models, because there is no group harmony to preserve among agents. The roles of controller and project manager are given to the AI.
The benefit of a competitive mechanism comes from generating several candidates and selecting the best one, not from agents trying harder. It depends on the diversity of the candidates and on the reliability of the selector.
| # | Rule |
|---|---|
| K1 | A competitive mechanism is opened only with a reliable selector: tests or measurable criteria, or a rubric fixed in advance, assessed by a judge running on a model different from the competitors', with the order of candidates alternated. All candidates start from the same point. |
| K2 | For each mechanism the diversity of the candidates is recorded: model, supplier or strategy. |
| K3 | By default there is a single candidate. Two or three for highly variable generative packages or where errors are costly, within the spending cap. |
| K4 | After selection, the criticism raised by the losing candidates is applied to the winner, through the reviewer. |
| K5 | Part of the evaluation criteria is not shown to the candidates, and judges rotate. |
| K6 | The winning margin, judge–human agreement (calibrated on a sample of human judgements of candidates) and cost per accepted increment compared with a single executor are measured. If the mechanism does not beat a single executor on a type of package, that type returns to a single candidate. |
| K7 | With strongly diverging proposals on a two-way door, the option with the lowest rollback cost is adopted. First, if the budget allows, a short test is run to discriminate between the options. |
| K8 | These cases are flagged "high divergence". The process reviewer examines all of them and gives them priority in the calibration sample (E6). |
| K9 | If divergences recur on the same theme, the AI Coordinator proposes a mandate review as a Do, translated into functions, costs, time and impact on users and data. If the theme cannot be expressed in these terms, it stays with the AI roles under K7 and K8. |
For each verification, the level of independence achieved is recorded: context, model, supplier or person. The package's risk class sets the minimum level. Guidance: for security and personal data, at least a different model.
4 bis. AI Squads and agentic Scrum
Organisational pyramid
AI roles are organised in a pyramid. For each level, tasks and competences are defined, so that each role is assigned an agent with a suitable model.
| Level | Examples | How it works |
|---|---|---|
| High | AI Coordinator, functional analyst, architects | Personas with a human professional profile, tied to functional and business objectives. The higher the role, the more specific it is to the project or domain |
| Middle | AI Scrum Master, reviewers | Coordinate and verify according to templates and criteria set by the AI Coordinator |
| Low | Executors, unit testers | Highly automated roles following basic collaboration rules |
- Each role has the core competences of its profession. For example, an architect knows the TOGAF ADM, within the terms of use of the standard (§5).
- Models of different origin are used where possible to create effective comparisons (§4).
- Each role is given a Mode and Role following the guidelines of the model provider, to make its behaviour predictable and controllable in different contexts (§9).
- Each profile has a Unit Cost, because AI is not free. Local engines have a cost tied to the use of local resources, that is machine hours at a declared rate. The Unit Cost is used to estimate and report the project's cost.
Digital Seniority
In an organisation every person works at the level of experience the task requires. Eiraman applies the same rule to agents. An agent's Digital Seniority is the combination of engine and reasoning level with which the AI Coordinator activates it. For example, in Claude: Haiku, Sonnet, Opus or Fable, each with a reasoning level from low to maximum.
| Level | Name | When it is used | Example configuration in Claude |
|---|---|---|---|
| SD1 | Junior | Repetitive tasks with an outcome a deterministic check can verify | Haiku, low reasoning |
| SD2 | Professional | Routine work on a clear specification | Sonnet, medium reasoning |
| SD3 | Senior | Local design choices, diagnosis, review of others' work | Sonnet, high reasoning |
| SD4 | Lead | Architecture, security, effects hard to undo, Do sheets, judging between candidates | Opus, high reasoning |
| SD5 | Principal | New or high-impact problems, by exception and with a recorded reason | Fable, very high reasoning |
- Catalogue. Every Role Profile lists the tasks and deliverables the AI Coordinator can assign to it, each with its minimum level and the matching configuration for every allowed tool (Claude Code, Codex, GitHub Copilot). The mapping from level to configuration is kept in a single map in the profile registry, re-checked at every model change (§9).
- Fallback. A task not in the catalogue runs at SD4. The AI Coordinator records it and proposes adding it to the catalogue (§11).
- Team membership. An agent joins a Scrum Team with the highest seniority required by the tasks it must perform in the Work Package.
- Verification. The independent reviewer or tester works at least at the level of the executor it verifies.
- Promotions and reductions. After two attempts failed for lack of capability, the AI Coordinator moves up one level and records it. The promotion uses the attempts allowed by the Work Package sheet (§6): if they are exhausted, it opens a decision point. In the retrospective it may lower a task's level if evidence shows unchanged quality at lower cost: a two-way door within the mandate's tolerance, a Do beyond it.
- Cost. Unit Cost is calibrated per level, and every run records the actual level, engine and reasoning (§7).
Teams and agentic Scrum
Agents work according to Scrum principles, adapted to collaboration between AIs:
- No Sprints or human timeboxes. The unit of delivery is the Wave, bounded by tokens, cost and duration (§5). Scrum's limits on team size do not apply: the limit depends on the LLM environments used.
- One team per Work Package. The AI Coordinator forms each team with the roles and competences the package needs, up to composing the squads of the Staff Planning.
- One AI Scrum Master per team. It coordinates the team's agents, maintains the Log Tracker along with the package and delivers to the AI Coordinator an activity report on the template the AI Coordinator specifies.
- Shared context, except for the tester. The agents of a team share the same context. The exception is the unit tester: it receives requirements, contracts, data and expected results (§2), but not the team's discussion, so as not to bias the tests. It may run on a different engine, external or local, or on the same engine without that context. For packages touching security or personal data the same engine is not enough: at least a different model is required (§4).
- Competing teams. The same Work Package may be assigned to several teams working in competition, with different engines or compositions. This is used when the generative part is particularly complex, such as writing documents, and under rules K1–K9. By default there is a single candidate (K3).
Scrum of Scrums and the AI Coordinator's role
Work is organised centrally by the AI Coordinator, which assigns and validates the teams' work. Compared with a Scrum Master it adds technical and compliance validation:
- it sets the quality and functional criteria to be checked for a package to be complete;
- it verifies correct execution at the end of each package (§6, Closure);
- it resolves dependencies between teams and closes the Wave only after the integrated increment has been verified.
Retrospective. At the end of each cycle the AI Coordinator analyses the Scrum Masters' reports and:
- optimises the composition of the teams, for example raising an architect's seniority level or changing the model for a role;
- reviews operational decisions.
Improvements that bring savings without reducing quality, or reducing it within the tolerance set in the mandate, are applied without involving the Human Manager. Any potential change to an approved Decision instead requires the Human Manager, with a SWOT prepared by the AI Coordinator (§3, Do).
Flexibility of Decisions. Compared with traditional Scrum, Decisions may be changed more flexibly, because scaling and coordinating AI Squads to handle change costs less. The cost of change and rework is estimated and reported in the Do record.
5. From Vision to release
Governing the scope
- The Vision becomes binding when the mandate is approved. Changing it opens a new project.
- Principles are frozen per version at the end of planning. If a Principle changes during installation, the AI Coordinator marks the version as failed, records the installed state and manages restore or transition to a new version.
- The success criteria of a version and of the project are based on KPIs measurable in the test procedures.
- Decisions may not violate a Principle. They are linked: changing one Decision may require changing the linked ones, which are then re-examined.
- Each Decision has an identifier, owner, status, rationale, linked Principles and dependencies. A new Decision refers to the one it replaces and to the packages to be re-examined. A saving that changes a Decision goes to the Human Manager even when it is within the quality tolerance.
- Each open point states which Wave it blocks and the criterion for closing it.
- The mandate contains the project's stop criteria: spending, number of Waves without an accepted increment, a negative POC.
Production cycle
All five phases are executed by the AI system, organised in Waves, under the same rules: 3D escalation, competitive mechanisms, evidence-based closure, cost recording. The Human Manager steps in only at the decision points of each phase.
| Phase | Who works (AI system) | What it produces | Typical competitive mechanisms | Human Manager decision |
|---|---|---|---|---|
| 1. Discovery | AI Coordinator, analyst and several exploring agents on different models, within guardrails | Problem, benefit, discarded alternatives, draft Vision; class assigned by the applicability gate (§10) | Divergence: several agents generate hypotheses independently. Convergence: the analyst selects and ties back to user evidence | Approves Vision, mandate and class; may relaunch an exploration round |
| 2. POC | AI Coordinator, analyst, architect, executors, tester | Explicit uncertainty, repeatable feasibility test, resources and access needed | Alternative tests on the same technical question, when the selector is measurable (K1) | Do only if the outcome is negative or requires new access or spending |
| 3. Design and planning | Analyst, application architect, infrastructure architect, AI Scrum Master, AI Coordinator | Business, application, data and technology views; contracts, backlog, Work Packages, profiles, cost estimate, test criteria; proposed Principles and Decisions | Alternative architectures assessed against a rubric fixed in advance | Approves Principles, Decisions with business impact and budget; Principles are frozen |
| 4. Scale | AI Coordinator, AI Squads with AI Scrum Master, testers and reviewers | Software increments closed on evidence | K1–K9 on generative packages | Governance cycle: periodic review and Do |
| 5. Acceptance and operation | AI Coordinator, testers, operations roles | Acceptance testing, release, manuals, service management | Alternative diagnoses of an incident | Acceptance of the result (UAT) and Do on operations |
The project may refer to the TOGAF® standard in phase 3, under the conditions applicable to its user. Capacity and budget set the degree of parallelism in every phase.
In operation, from level 2, SLOs, incident management and blameless postmortems apply, and feed the retrospective (§10). When the error budget is exhausted, the environment applies a Deny to non-corrective releases.
Design Thinking delegated to AI (phase 1)
Left free, AI engines are powerful gatherers and spreaders of information, but they tend to diverge. Discovery therefore follows Design Thinking with precise roles and boundaries.
- Divergence. Several models, with defined roles and behaviours, independently generate and detail hypotheses, problems, benefits and principles of the Vision. Guardrails: maximum number of rounds, permitted sources and data, criteria for discarding a hypothesis.
- Human Manager gate. At predefined gates the Human Manager may give new inputs, which trigger a new round of divergence.
- Convergence. A single model, in the role of functional analyst, gathers the contributions, reviews them while coordinating the other agents and relates them to user evidence. It produces the project's basic idea, the draft Vision and a first version of Scope Management: Vision, Principles, success criteria and open points.
- The Human Manager approves the Vision or relaunches the exploration.
POC, design and planning
- POC and MVP. The functional analyst validates feasibility, theoretically or by asking the AI Coordinator for small trial Work Packages. The resources needed in terms of computing and access are also validated. For example, the ability of a local engine to process a document of the expected size within the expected time and cost.
Design and planning. The functional analyst works first with the application architect, then with the infrastructure architects and the AI Scrum Master. Together they produce:
- the architectural design;
- the Product Backlog and the workstreams;
- the cost estimate for the AI component;
- the initial performance estimate, which the tests will update in the Performance Analysis.
The Human Manager validates the proposed solutions, which become Principles and Decisions. At the end, the Principles are immutable for that version. Design follows the architectural guidelines of the vendors or open source communities of the chosen technologies, and the architects have these competences in their profiles.
Waves and the governance cycle
Wave. The unit of technical delivery in every phase; it follows the pace of the AI.
- It has a spending cap and a maximum duration; whichever is reached first applies.
- At 80% of spending the AI Coordinator flags it. At 100% a Deny on new work is triggered and the Wave closes with a checkpoint.
- Waves follow one another automatically within mandate and budget.
- A Wave closes after verification of the integrated increment.
Governance cycle. The Human Manager's unit of decision, on a calendar cadence. It closes with a single management review containing:
- deliveries and acceptances;
- spending and cost per accepted increment;
- state of the drift budget (E5);
- number of high-divergence cases (K8; individual cases stay with the process reviewer) and recurring themes (K9);
- open Do escalations;
- proposal for the next cycle.
If the cycle expires without the next one being approved, running Waves finish the active package and open no new ones.
Escalation load. An indicator of the governance cycle; it never blocks a due Do. It is read together with under-escalation.
- Ordinary Do escalations in every phase and K9 escalations are counted.
- Urgent Do escalations, counted separately, and decisions planned by the phases are not counted.
- Non-urgent Do escalations are grouped in the cycle review, except those blocking the critical path.
- Guidance. Weekly cycle; a reference of 3 ordinary Do per cycle; about 30 minutes of the Human Manager's attention per week. Each user may set their own values in the mandate. The cycle review always shows the declared value next to the observed one. The value changes only at the cycle review.
6. Work contracts and verification
Composition
The components (Backbone, Brain, Hands/Foot/Eyes/Ears, Hairs) are defined in §6 bis. Each component declares its contract, data, dependencies, integration test and, if peripheral, a check of behaviour when it is removed. The first usable path runs through Backbone and Brain and includes the essential interfaces. Priority and detailed rules are in §6 bis.
Minimum Work Package record
The record holds:
- project and Wave, ID, starting revision;
- success criteria and exclusions;
- Principles and Decisions, dependencies;
- profiles and versions;
- budget and attempts allowed;
- expected result and verifier;
- resumption procedure.
The final account includes all candidates, including discarded ones.
Functional criteria are written in Given/When/Then form. Non-functional criteria refer to the ISO/IEC 25010 characteristics. A Work Package is ready only when its criteria are executable.
Closure
- Positive evidence. The AI Coordinator closes the package when the mandatory checks on the identified candidate have passed and the evidence is identifiable. A change to the candidate reopens the affected checks.
Dissent or missing proof. The package stays open.
- With a clear requirement, the test is repeated or a second verifier is assigned.
- With an ambiguous requirement, a decision point is opened.
- Outcome, dissent and the rationale for closure are recorded.
- Tests. Component, integration, system and acceptance. Mapping to «DevSecOps and tests»: unit test = component; functional tests with script or simulated user = integration and system; UAT = acceptance.
- Deterministic anchors. At every release, static analysis, dependency and licence analysis and secret scanning are run. At level 2 dynamic scanning is added. AI roles interpret the results; they do not replace them.
DevSecOps and tests
Work follows DevSecOps practices where applicable:
- Git log of the application and its versions, with comments written to be read by people as well.
- Security by Design, with static analysis (SAST) and, at level 2, penetration testing (§10).
- Highly automated tests, run by dedicated agents:
| Type | Who and how | Outcome |
|---|---|---|
| Unit test | At the end of each Work Package, run by the independent AI tester. They also check security and performance components | They update the Security Risk Posture and the Performance Analysis |
| Functional test with script | The agent runs the test script, records the logs and checks completion or failure | For gross errors that affect neither quality nor Decisions, the agent fixes them on its own, as a two-way door |
| Functional test with simulated user | An agent simulates a typical user and uses the application as a person would | Run in stable environments, because it costs more |
| UAT (final acceptance) | A person performs the business task, and the AI assists by recording observations and missing information | The Human Manager decides on acceptance |
Functional tests are human-supervised: the person may watch them but does not need to intervene for them to proceed. UAT is AI-supervised: the person executes, the AI records.
6 bis. Composable architecture
The idea behind an application is broken down into components tied to functions, modelled and developed independently in Work Packages. In Vibe Coding the key point is the order of construction. AI's flexibility makes adding pieces easy, and without a catalogue and an order you build overly complex patchworks.
| Component | What it is | Priority rule |
|---|---|---|
| Backbone | The core components needed for the core deliverable | Built before all other components. It covers, in minimal form, all the main paths of the core deliverable |
| Brain | The application's logic, more and more often made of internal or external AI engines | Brain tasks are catalogued as trusted or untrusted. This determines which tasks are delegated to the engines and which stay under deterministic control or require a Do (§3, §7) |
| Hands, Foot, Eyes, Ears | The interfaces through which the application communicates and interacts with users. They are often the part that grows most | They rest on Backbone and Brain. They are developed early in essential form, within the first usable path, and in advanced form only once the previous components are stable |
| Hairs | The most peripheral functions, added or removed at any time, even for small specific tasks | Last in priority; they are added or cut at any time. Before removing one, check that the core passes regression |
The Product Backlog labels each workstream with its component and priority, and links it to the Decisions and open points it depends on.
Architecture document. The architecture document, developed according to the TOGAF business, applications, data and technology views, specifies at the data and infrastructure levels the best practices used to design and integrate the architecture in a composable way. For example, requests to a local LLM engine are handled differently from those to an external engine: small packaged requests in the first case, a single request in the second. The choice is measured on the same workload, comparing quality, latency, cost and data constraints.
7. Environment, execution and agent security
Execution and recovery
Project opening. The AI Coordinator:
- resolves the version of the method and the profiles;
- checks the repository state and available capabilities;
- configures runners and connectors;
- tests the authorisations needed.
Access that requires the account holder opens a narrowly scoped request. The environment enforces tool constraints and keeps secrets in the platform's credential store.
- Executions. Each execution has an ID, persisted state, input version, checkpoint, budget and attempt limit.
- Resumption. After an interruption the AI Coordinator reconciles the state with the effects already produced before restarting. If the AI Coordinator is unavailable, the runtime preserves the work and prevents new uncontrolled operations. On restart, the AI Coordinator checks the last delivery, then resumes or restores the previous version.
Agent security and traceability
- Security Risk Posture. It identifies the security requirements and classifies the application by needs, context and type of data processed. It lists the compliance requirements to apply (for example GDPR), the personal data and how they are handled, the security perimeters, the open ports and services, and the specifications that ensure the security level of each architectural component. The approach is Security by Design.
- The Security Risk Posture also includes an Agents section. For each role it lists permitted tools, network destinations, readable data and irreversible actions, which are always Do. Reference: OWASP Top 10 for LLM and agentic applications.
- Brain tasks catalogued as untrusted (§6 bis) are not delegated to an engine without a deterministic check of the result. If the action is irreversible, it is a Do.
- Mandatory negative test. An input carrying a hostile instruction must produce a recorded Deny.
- Each run records the profile hash, the exact model identifier, the effective configuration and the Unit Cost. The product includes an SBOM. The aim is traceability, since LLM output cannot be reproduced deterministically.
- The mandate contains the table of data classes per provider: which providers are allowed for each class, taking retention and training into account.
Delegation considers separately the origin of the data, the role's permissions, the permitted destinations and reversibility.
8. Documentation
| Level | Audience | Content | Verified by |
|---|---|---|---|
| Strategic | Human Manager, who approves | Vision, Principles, success criteria, mandate | Human Manager |
| Managerial | Human Manager, who reads and decides by exception | Project sheet, milestone plan, high-level architectural view, decision sheets, business risks, dashboard, cycle review, UAT outcome, cost report, security and performance summaries | AI reviewer |
| Operational | Agents | Architecture, backlog, Work Packages and Staff Planning, Log Tracker, detailed registers, test evidence | AI system |
Writing rules for the Human Manager.
- Business language.
- Open with the four questions: what has changed, what is being asked, by when, what happens if there is no answer.
- Changes since the last reading come first.
- Length limits: one page per decision sheet.
- Outcomes, not procedures.
- Every verifiable statement is linked to evidence, and the AI reviewer checks the link.
- Comprehension test by an agent with the Human Manager profile, calibrated once by the Human Manager on about 5 documents.
- Minimum set per level, as listed in the requirements in §10.
- Bad news first: failed tests, open risks, dissent, rejections, missing decisions.
- Completeness check: an omission compared with the operational registers blocks delivery of the document.
- Third-party evidence pack: on request, for a single release; at level 2 it is ready at every release. It contains mandate, class and level, profiles and versions, checks and outcomes, independent verifications, accepted risks and acceptance.
- Qualified templates: each document type has a versioned template qualified by the maintainers.
Release.
- Installation and user manual at every level; Executive Description and Performance Analysis where the level requires them. They are verified at every release.
- The Performance Analysis compares the product's performance with expectations.
- The cost report shows development costs and running costs of the application separately.
- Progress expressed as a percentage states its denominator.
Governance artefacts.
- High Level Plan: the high-level plan of activities, presented to the Human Manager as milestones.
High Level Architectural View: one page, with a drawing, showing the Human Manager what the product is made of, in terms understandable to non-specialists:
- the points of contact with people, for example a web page, an app or an email;
- where the data lives, for example a database, a document store or a spreadsheet, and which data classes it holds;
- the external services and AI engines used, distinguishing those local to the organisation from external ones;
- the main flows between the parts and the boundaries, that is what leaves the organisation and who can access it.
It does not report operating systems, languages, versions, libraries or configurations: those details stay in the operational architecture document (§6 bis), from which the view is derived. The AI Coordinator updates it when a part is created, changes or disappears. A change that adds an external service or moves data outside the organisation is a Do.
- Risk Log: the risks of project failure and how they are managed according to Risk Management. Business risks reach the Human Manager; the detail stays operational.
- Executive Description: a short description of the product and its functions, to present it to non-specialists. The AI Coordinator keeps it updated and verified.
- Product Backlog: contains the workstreams the teams can carry out, labelled and ordered according to the composable architecture (§6 bis).
- Work Packages and Staff Planning: define the packages and the competences, i.e. the AI roles, down to the composition of the teams (§4 bis).
- Performance Analysis: reports the product's most significant performance figures, for example the time to produce a document. It is estimated during design and updated with the tests.
- Log Tracker: not designed to be read by people. It is the general log of all activities, used by the AI Coordinator to follow the teams' progress.
- Progress dashboard: an HTML page updated by the AI Coordinator, with the percentage of progress of each phase, stating its denominator. It also contains a tree of the Work Packages (completed, in progress with their percentage, to do) with the cost estimate of each; for each package the Human Manager sees description, deliverables and team composition by Role Profile. A linked page gathers the project's strategic and managerial documents.
Shape of the control artefacts. In Scrum terms, every project and every Human Manager decide the shape of the artefacts they use for control. The dashboards, views and documents described here are a starting point: the Human Manager adapts them within the application's development and control cycle, and the choice is recorded as a project decision. The minimum content required by the drafting rules and by the level (§10) stays fixed.
Measurement. For each governance cycle, reading minutes, decisions, clarification questions and intercepted omissions are recorded.
9. Role Profiles and maintenance of the method
A Role Profile contains:
- purpose, responsibilities, permitted and forbidden actions, communication contract;
- normative sources with precise references to the clause of the standard each rule derives from;
- mandatory deterministic tools and how to interpret their results;
- qualification suite with known-answer cases;
- enabled models and reasoning level;
- declared limits: if a package falls within them, the project leaves the scope;
- curator and reviewer, date and expiry of the qualification;
- the role's document repository, i.e. the sources where the agent looks for information for its tasks. For example, for an architect of a cloud vendor, the site with product specifications and reference architectures;
- enabled engines, cloud and local, with minimum requirements. For a local engine, for example, the minimum size in billions of parameters;
- task catalogue by Digital Seniority level (§4 bis): which tasks the role can perform and with which engine and reasoning level. It replaces the original task matrix by engine and reasoning level. The AI Coordinator picks the configuration for each Work Package;
- Mode and Role following the model provider's guidelines;
- the profile's Unit Cost for each engine and Digital Seniority level;
- a catalogue of tasks and deliverables the AI Coordinator can assign to the role, with each one's Digital Seniority level and activation configuration for every allowed tool; tasks outside the catalogue run at SD4 (§4 bis).
Structure in the Git registry. Each Role Profile is a folder in the Git registry, with two kinds of files:
- instantiation Markdown files: description, purposes, methods, communication rules, permitted and forbidden actions (for example, an architect does not change the code and a developer does not change the architecture documents), document repository;
- descriptor files: enabled engines, task catalogue by Digital Seniority level, Unit Cost, qualification.
The AI Coordinator learns its own profile and the necessary competences from the Git registry, and instantiates the Role Profiles each phase requires.
Publication. First an LLM runs the pre-assessment: suite, consistency with the sources, format, search for anomalous instructions. The LLM may reject a profile but not approve it. Then the domain expert reviewer publishes it as a signed version.
Maintenance rules.
- Four eyes: the author of a change may not be its reviewer.
- Each domain has a primary reviewer and a deputy: cloud architecture, security, application and data architecture, testing and quality, privacy, legal and compliance.
- At every model change the suite re-runs all profiles, and the reviewer examines only the differences in behaviour.
- A profile not requalified within the deadline is suspended.
- A domain without a reviewer may not publish profiles.
- Contributors assign or license their contribution under the organisation's rules.
- The reviewer answers for the profile's correctness against its sources at the time of review, not for the projects that use it.
- The same rules apply to document templates and to the gate checklist.
10. Applicability levels
Principle
In Eiraman projects, specialist competence lives in qualified Role Profiles rather than in the presence of specialists in every project. The risk that the business owner cannot assess must therefore be limited from the start. Every adoption of Eiraman has a qualified level and every project has a class. A project may run only if its class does not exceed the qualified level of the adopter. Classes also apply to the deliverables a product generates. Whoever uses the method for themselves stays at level 0. To move up, they must meet the requirements of the next level and demonstrate them with evidence.
Project classes
| Class | Users | Data | Exposure | Examples |
|---|---|---|---|---|
| 0 | Only the adopter | No personal data of others | Local or none | Personal tools, document generators for own use |
| 1 | Colleagues in the same organisation | Ordinary personal data of colleagues | Internal network or cloud with corporate identity | Departmental applications |
| 2 | Customers, suppliers or an authenticated public | Ordinary personal data of third parties, limited volumes | Internet with authentication | Portals, self-service, documents for customers |
Out of scope, at any level:
- special-category or criminal-offence data (Arts. 9–10 GDPR);
- children's data;
- large-scale processing;
- processing for which screening makes a DPIA mandatory (Art. 35 GDPR);
- automated decisions about people (Art. 22 GDPR);
- payments handled in the product's own code;
- AI that is prohibited or high-risk under the AI Act;
- an owner subject to the NIS2 directive;
- installable distributed software or devices subject to the Cyber Resilience Act, pending dedicated requirements;
- sector-specific regulation;
- physical safety.
Applicability gate
An AI compliance role assigns the class using a versioned checklist qualified by the maintainers. The gate runs when the project opens, at every Wave and at every change of mandate. If an exclusion criterion is triggered, or the case is doubtful, the project is out of scope and the business owner is informed.
The checklist separates exclusion criteria, listed above, from requirements, which must be met but do not exclude. For example:
- transparency towards users of chatbots and generated content (Art. 50 AI Act);
- a DPO already appointed where the organisation is required to have one (Art. 37 GDPR).
The checklist is not a substitute for legal advice.
Requirements per level
Requirements are cumulative.
Level 0 · Personal use
- Framework: basic qualified Role Profiles. Static analysis, dependency and licence checks, secret scanning at every release. Documents for the Human Manager: project sheet, decision sheets, governance cycle review, installation and user manual.
- Organisation: the adopter is owner of, and responsible for, the project and what it produces.
- Evidence: no prior evidence.
Level 1 · Internal team. To move up from level 0:
Framework:
- security and privacy profiles qualified for class 1;
- authentication only through the corporate identity;
- backup and restore test before release;
- rules on log content and retention;
- DPIA screening at every change of processing;
- procedure for notifying breaches within 72 hours (Art. 33 GDPR), written for the Human Manager;
- additional documents for the Human Manager: management summary of the Security Risk Posture, processing record for the owner, Executive Description.
Organisation:
- identified owning organisation;
- formal mandate to the Human Manager;
- corporate IT policies as a binding input to the mandate;
- DPO appointed, where the organisation is required to have one.
Evidence: experience at level 0 with measured results:
- under-escalation within threshold, after calibration;
- detection of a suite of deliberately seeded vulnerabilities at least at the threshold set by the maintainers;
- no open critical finding at release.
Level 2 · External users. To move up from level 1:
Framework:
- OWASP ASVS level 1 requirements selected and verified;
- dynamic scanning at every release;
- authentication and payments only through certified providers;
- operation with SLOs, incident management and postmortems;
- a policy for updating dependencies and fixing vulnerabilities, blocking release if the product is offered in a commercial activity (Directive (EU) 2024/2853, Art. 11(2));
- additional documents for the Human Manager: penetration test summary, Performance Analysis;
- third-party evidence pack ready at every release.
Organisation:
- external penetration test bought as a service, at the first release and then periodically; the AI Coordinator prepares its scope and authorisation, the Human Manager decides its cost;
- contracts with suppliers processing data (Art. 28 GDPR).
- Evidence: operation at level 1 for a defined period without serious incidents; a positive penetration test on the first class-2 release.
Moving up and down
Moving up. It is a one-way door and therefore a Do. The AI Coordinator presents a management dossier with:
- requirements met;
- evidence;
- recurring costs;
- residual risks.
An independent reviewer checks the evidence before the Do.
- Automatic downgrade. If a requirement lapses (suspended profile, expired penetration test, open serious incident), the environment applies a Deny. Only corrective releases are allowed until the requirement is restored or the project returns to the permitted class.
Class change. It is always a Do and counts towards the drift budget. If the new class exceeds the level, the Human Manager chooses to:
- reduce the scope;
- hand the critical component to a certified provider;
- take that project out of the method.
Open points
| Point | Blocks | Closure criterion |
|---|---|---|
| Numerical thresholds: vulnerability suite, under-escalation, length of operation at level 1 | First move to level 1 | Proposal by the maintainers after the NUR pilot, approved by the Human Manager |
| Frequency of the penetration test | First move to level 2 | Economic decision by the Human Manager on the AI Coordinator's proposal |
| Content of the gate checklist | Level 0 | Versioned checklist qualified by the maintainers |
| Interface for the Human Manager (dedicated app or VS Code extension) | First adoption outside the pilot | Path assessed in the NUR pilot: opening the project, granting the mandate, deciding an exception, consulting the evidence, accepting the result. The AI Coordinator does all the technical work; the choice is the Human Manager's |
11. Projects, partial application and feedback into the method
Project sheet. It identifies:
- application, users, deliverables, repository and revision;
- Eiraman version used, class and level;
- Eiraman components built into the product, and adaptations;
- success criteria.
The AI Coordinator keeps two separate links: between package and software release, and between a run of the product and the deliverable it generated. For each adopted component, where it runs and which version is recorded.
Partial application.
- A product that incorporates parts of the method publishes a declaration of partial conformity, listing the rules applied and those not applied. It may not present itself as Eiraman-conformant without this qualification.
- Applicability classes also apply to the product's deliverables. For example, a level-0 adoption may not use NUR to produce documents for customers, which are class 2.
- Every component that can be incorporated declares contract, regression tests, version and the rules it implements.
Feedback into the method.
- Observation. The retrospective links a reproducible case, the rule applied, the outcome and the cost. The AI Coordinator identifies whether the cause lies in data, application, environment or method.
- Proposal. A specific fix stays in the application backlog. A reusable rule or component needs a contract, test, limits and impact on existing projects. Any change to Principles or Decisions follows the required approvals.
- Adoption. The approved change is versioned, with compatibility, regression test and the projects adopting it. The project that prompted it keeps a reference to the change. Another project may adopt only the relevant component.
The method as a project. Managing the method is itself an Eiraman project, governed by the same rules as any other. It covers:
- the specification;
- the Role Profiles;
- the document templates and the gate checklist;
- the tools, such as the Manager view;
- the site that presents it.
The project has:
- a Human Manager, that is the owner of the method;
- an AI Coordinator;
- a mandate, a registry and a Manager view.
Proposals coming from the return to the method enter its backlog as Work Packages.
The agents of this project may draft and pre-assess new versions of the Role Profiles, templates and checklist. Publication, however, follows the rules of §9: an expert domain reviewer, other than the author, decides. Every change to the specification and every external publication, including the site and the repositories, is a Do of the Human Manager. A Role Profile published by the reviewer leaves the organisation only with a Do.
Change log
0.3 (25 November 2026). Reinstates from the original version of the method the operating model and the framework map (§1), AI Squads and agentic Scrum (§4 bis), Design Thinking delegated to AI and the detail of POC, design and planning (§5), DevSecOps and tests (§6), the composable architecture (§6 bis), the governance artefacts (§8) and the full content of the Role Profiles (§9). It adds to the governance artefacts the High Level Architectural View for the Human Manager, the Work Package tree with cost estimates and the project documents page in the dashboard, and the rule that the shape of the control artefacts is a project decision (§8). Managing the method and the Role Profiles becomes itself an Eiraman project (§11). It introduces Digital Seniority: levels SD1–SD5 of engine and reasoning, a task catalogue in every Role Profile, fallback to SD4 (§4 bis, §9).
0.2 compared with 0.1. Version 0.2 revises responsibilities, applicability levels, the governance cycle, escalation, competitive mechanisms, documentation, Role Profiles and conformity, and introduces the following rules.
| ID | Rule introduced |
|---|---|
| P1 | Stop criteria in the mandate |
| P2 | Given/When/Then criteria, ISO/IEC 25010, definition of ready |
| P3 | Deny on non-corrective releases when the error budget is exhausted |
| P4 | Agent security: Agents section, negative test, profile and model hashes, SBOM |
| P5 | Data classes per provider |
| P6 | Minimum levels of verification independence |
| P7 | Local/external boundary of the Development Environment |
| P8 | E6 calibration in the first project of every new adoption, not only in the NUR pilot |